Water treatment plant, Eindhoven, Netherlands

  • Type de bâtiment:
  • Bâtiments industriels
  • Infrastructure
Plein écran Fermer Street view

For the raising of the sedimentation basin within the sewage treatment plant in Eindhoven, the precast elements are connected to each other in a fast and efficient way with the Peikko SUMO® wall shoe connection. 

This dry connection consists of a SUMO® Wall shoe cast in one element and an HPM® anchor bolt cast in the other element. Together this forms the wall shoe joint that absorbs tensile loads. To provide protection against corrosion, the connections are galvanized in this project.

Détails du Projet

Développeur:
Waterschap De Dommel
Entreprise de construction:
Van Boekel Bouw & Infra
Pré-fabricant de béton:
Haitsma Beton
Année de réalisation:
2019
Année de livraison:
2020

Consultez nos experts