Multipurpose Commercial Building for AS Elevators, Steinach, Switzerland

  • Type de bâtiment:
  • Bâtiments industriels
  • Bâtiments à bureaux
Plein écran Fermer

13 months construction time with composite structure from Peikko.

A new multipurpose commercial building was erected in Steinach for the elevator manufacturer AS Elevators.

The building complex consists of a main building with a production/warehouse hall as well as a head building with office space and a smaller commercial hall, which is intended for rental.

The complete planning was done with BIM-3D and included complex connections in the area of the crane runway due to limited room height. The connections were worked out together with Peikko.

Thanks to Peikko's DELTABEAM® Frame composite frame system, spans of up to 13 meters could be achieved and the construction time was only 13 months.

Lire la suite down-arrow.png

Détails du Projet

Développeur:
METHABAU
Entreprise de construction:
METHABAU
Designer structurel:
METHABAU
Architect:
METHABAU
Année de réalisation:
2018
Année de livraison:
2018