The strategic purchaser of Losinger-Marazzi SA, Mr. Thomas D'Halluin, searched a solution to erect high columns on single foundations without props, while maintaining a high level of site-safety.  Their application meant to install columns, free of props, without having to climb on a stair to fix propping or to unplug the crane's hook. Peikko Column Shoes ended up to be a used method in this project. This project revealed to be trendsetting.

We're happy having found a solution for this classic problem. We've heard many times, that columns should be preferably restraint with their foundations, but til now no commercial solution was available yet.

Bertrand Faucherre, Dr. Denis Clément

Détails du Projet

Taille du projet:
20 000 m2
Étages:
3
Designer structurel:
Thomas Jundt Ingénieurs Conseils SA Geneva
Pré-fabricant de béton:
Bétontec
Année de réalisation:
2010
Année de livraison:
2011